 | Midway Substation | 500KV breaker change out. Remove existing oil HVCB, conduit, grounds and rigid bus. Install SF6 HVCB conduit, grounds, wiring and aluminum buswork. | 6,800 man hours |
 | Hardwick Substation | Replace 115kv Transformers. Remove transformers, structural steel, strain bus, hard bus etc. Install new transformer, structural steel, strain bus switches, conduit, grounding and control wire. | 1,100 man hours |
 | Cottonwood Substation | Add 12,000 feet of station ground grid. 500 MCM CU, 276 ground rods and 250 MCM CU tails to the existing grid. | 1,400 man hours |
 | Lockeford Substation | Reconfigure the 230kV to a ring bus, install Transformer Bank 2, re-conductor the 60kV bus with Breaker and PT replacements and install new control room switchboard panels. | 4,700 man hours |
 | Taft Substation | Install 115 KV ring bus inside existing 115 KV substation. Remove steel, breakers, conduits and strain bus. Install 6 HVCB, 18 115 KV switches, dead-end towers, switch structures, strain bus, rigid bus, conduit, and station grounds. Pull and terminate control wiring. | 6,500 man hours |
 | Metcalf – Moss Landing Substations | 230kV Breaker, structure, and switch replacement with strain bus. | 6,450 man hours |
 | Los Banos Substation | Replace 500kV Transformer Bank 1 and 13.8 Tertiary with 230kV switch replacement. | 10,500 man hours |
 | Salinas Substation | 115kV and 60kV Bus, Transformer, Switch, and Breaker Replacement. | 47,000 man hours |
 | Eight Mile Substation | Install Transformer Bank 2 230kV / 21kV with 4 new 21kV breakers, 230kV Circuit Switcher and Breaker. | 4,100 man hours |
 | Gates Substation | Replace 500kV Circuit Switcher with a SF6 Breaker and disconnect switches with new below grade conduit duct bank and control circuits. | 4,250 man hours |
 | Bellota Substation | Replace 115kV Bus 1 and Bus 2. | 7,500 man hours |
 | Rector Substation | Replace 220kV Bus #2 | 5,700 man hours |
 | Mesa Substation | Install 2 – 115kV Shunt Capacitor Banks, Breakers, Bus and Structures. | 6,700 man hours |
 | Midway Substation | Replace 3 – 500kV Circuit Breakers, Switches, and Bus. | 3,250 man hours |
 | Villa Park Substation | Replace 14 – 66kV Circuit Breakers | 2,150 man hours |
 | Bassett Substation | Replace 18 – 22kV Circuit Breakers. | 3,305 man-hours |
 | Midway Substation | Remove 500kV Circuit Switcher and install CB 5212. | 4,370 man hours |
 | Midway Substation | Transformer Bank 1 230/115kV Switch Upgrade. | 2,750 man hours |
 | Midway Substation | Replace Transformer Bank 2 and re-conductor 115kV Bus Section “D” | 6,770 man hours |
 | Stroud Substation | Replace 70kV switchyard and control room. | 4,150 man hours |
 | Henrietta Substation | 70kV Breaker(s) install 70/21kV Transformer Bank 2 | 8,125 man hours |
 | Midway Substation | Replace 6 sets of 500kV Air Switches | |
 | Sneath Substation | 70kV Ring Bus and MPAC / Battery Building | 11,700 man hours |